2017 Street Paving & Maintenance Schedule

Pavement Preservation Work


The Agawam Department of Public Works (DPW) will be performing pavement preservation work on the following streets throughout the months of March and June:

Fog Sealing Only


  • Carr Avenue
  • Colemore Street
  • Nile Avenue
  • North Street Extension
  • North West Street (North Street Extension to North Westfield Street)

Crack Sealing Only


  • Barry Street (Pine Street to Connecticut State Line)
  • Cooper Street
  • Katherine Drive
  • Rowley Street
  • Wagon Wheel Drive (From House Number 75 North to Anvil Street)

Fog & Crack Sealing


  • Elm Street
  • Leonard Street
  • North Street
  • Pheasant Run Court
  • Red Fox Drive
  • Silver Street (Almgren Drive to Elm Street)
  • South Westfield Street (From House Number 703 to Connecticut State Line)
  • White Fox Road (South West Street to Partridge Lane.)

Microsurface


  • Bowles Road
  • General Abrams Drive (Almgren Drive to Bowles Road)

Reclamation Work


The Agawam DPW will be performing reclamation work on the following streets in the summer of 2017.
  • Barry Street (Pine Street to South Westfield Street)
  • Potomac Place
  • Reed Street
  • Rugby Road
  • Virginia Street
  • Washington Avenue (Suffield Street to Reed Street)
A definitive construction date has not yet been set.

Parking/Avoid Area


Residents are asked not to park their cars on the street during these times and avoid the area if possible. The construction may cause traffic delays or detours so residents are encouraged to plan accordingly.

Construction Dates/Streets Subject to Change


Please be aware that the construction schedule dates are subject to change due to unforeseen circumstances such as inclement weather or necessary emergency work. The order of construction work, as well as the addition or removal of streets from the above list, is at the discretion of the Agawam DPW.

Contact Information


Additional information will be posted on this website as it becomes available. If you have any questions, please do not hesitate to contact Michael F. Albro, P.E., the Assistant Town Engineer or Michelle C. Chase, P.E., the Town Engineer, using the contact us form.